Iteration 001 Plan — Architecture Alignment

1. Iteration Overview

  • Iteration: 001
  • Phase: Brownfield Construction / governance alignment
  • Status: Planned; dates and named staffing require maintainer assignment
  • Goal: Make current-state architecture, safety traceability, maturity claims, and workload evidence maintainable automated governance assets.

2. Goals and Evaluation Criteria

Goal Pass condition
Validate baseline decisions Maintainer review records accept/amend/supersede outcome for SAD and ADR-001–005.
Automate maturity consistency CI or a documented release check detects contradictory stable/experimental/research/roadmap labels.
Complete adapter safety inventory Every network-capable adapter maps to scope, approval class, credential behavior, timeout, and negative tests.
Establish workload evidence Source-ingest and concurrent-mission baseline receipts state revision, command, workload, environment, samples, and percentiles.
Triage debt markers Each in-scope marker is actionable, intentional, or obsolete with owner/disposition.

3. Scope of Work

In scope: SDLC artifact review; canonical repository identity decision; maturity audit design/implementation; adapter safety/test mapping; workload benchmark design/execution; debt-marker triage.

Out of scope: Microservice rewrite, hosted multi-tenancy, roadmap feature implementation, unsupported stability promotion, or live offensive testing beyond authorized benchmark environments.

4. Task Breakdown

ID Task Owner role Dependencies Estimate Deliverable
I001-01 Review SAD and ADR-001–005; record conditions Architecture steward + maintainer None 1 day Review log / amended ADR status
I001-02 Reconcile package and canonical tracker repository identity Release integrator Owner decision 0.5 day Metadata ADR/change
I001-03 Specify maturity vocabulary, sources, and conflict rules Requirements + evaluation steward ADR-005 0.5 day Decision table/spec
I001-04 Implement maturity consistency audit and seeded tests Implementer + test engineer I001-03 1–2 days Script, tests, CI/release hook
I001-05 Inventory network-capable adapters and risk metadata Safety reviewer Arsenal catalog 1 day Safety coverage matrix
I001-06 Close missing scope/approval/credential/timeout tests Implementer + safety reviewer I001-05 1–3 days Tests and adapter fixes
I001-07 Define source-ingest/concurrency workloads and metrics Test architect NFR-11 0.5 day Benchmark specification
I001-08 Run baselines and retain receipts Test engineer I001-07 1 day Versioned baseline report/receipt
I001-09 Triage source/script TODO/FIXME/HACK markers Maintainer Code inventory 0.5 day Triage list / issues

5. Milestones and Deliverables

  1. M1 — Baseline accepted: Review outcomes and repository identity decision recorded.
  2. M2 — Governance automated: Maturity audit passes valid state and fails seeded contradiction.
  3. M3 — Safety inventory complete: No unidentified network adapter; test gaps have owners or fixes.
  4. M4 — Measurements retained: Baseline receipts are reproducible and cited by NFR/test artifacts.

6. Resource Allocation

Roles may be combined, but architecture and safety review must be explicit for trust-boundary work. Capacity is not assumed; maintainers must assign names and dates before iteration start. Parallelize I001-03/I001-05/I001-07 only after I001-01 establishes the governing baseline.

7. Risks and Mitigations

Risk Mitigation
Owner review unavailable Keep retrospective status explicit; do not fabricate approval; defer status promotion.
Adapter inventory misses dynamic paths Derive from catalog plus runtime tool registration and seed a completeness test.
Benchmarks vary by host/provider Record environment and separate deterministic/local/live outcomes.
Maturity rules create false positives Use an explicit decision table, authoritative-source precedence, and seeded examples.

8. Dependencies

  • Upstream: accepted requirements/NFRs, SAD, ADR-003/004/005, canonical tracker config.
  • External: maintainer decision on repository identity and review conditions.
  • Downstream: release quality gates, construction-ready status, future capability promotion.

9. Testing and Validation Plan

  • Run build/type/lint and affected Vitest/script suites for any implementation change.
  • Seed at least one contradictory maturity label and one unclassified network adapter to prove new audits fail.
  • Validate benchmark receipts by rerunning their documented command on the recorded environment or classify non-portability.
  • Run git diff --check, AIWG citation/reference checks, and traceability/index diagnostics before closure.

10. Change Control

Scope changes require a recorded rationale, impact on goals/dates/risks, and maintainer approval. A request to implement a hosted/distributed/autonomous architecture exits this iteration and starts new inception/architecture work.

11. Review and Retrospective

At iteration close, review each pass condition, unresolved risk, and deferred measurement. Record what automation caught, false positives, missing evidence, and any required template/process updates. Dates are scheduled when maintainers assign capacity.

References

  • @.aiwg/architecture/software-architecture-doc.md — Open architecture questions and review log.
  • @.aiwg/architecture/adr-003.md — Adapter safety controls.
  • @.aiwg/architecture/adr-005.md — Maturity governance.
  • @.aiwg/requirements/nfr-register.md — NFR-09, NFR-11, and NFR-12.
  • @.aiwg/testing/test-strategy.md — Required test and measurement policy.
  • @.aiwg/intake/risk-screening.md — Risks driving iteration priority.
  • @package.json — Repository/package identity and scripts.
  • @src/arsenal/catalog.ts — Adapter inventory source.